RNS Number : 6833A
Hochschild Mining PLC
24 January 2024
 

 

 

 

 

 

_____________________________________________________________________________________

24 January 2024

 

 

 

Production Report for the 12 months ended 31 December 2023

 


Eduardo Landin, Chief Executive Officer said:

"Our operational team delivered a robust performance in the fourth quarter of 2023, and we have therefore ended the year at the top end of our revised production guidance with costs anticipated to be in line with expectations. I am also very pleased with our safety and environmental performance, where we achieved our best results in recent Company history.  

 

In Brazil, we are in the final stages of the Mara Rosa project's construction and commissioning phases and are looking forward to the first gold pour in February. This exciting new mine forms a key part of our recently announced growth strategy and is set to enable Hochschild to increase output this year by over 15%."

 

Operational highlights

§  Full year attributable production[1]

186,091 ounces of gold

9.5 million ounces of silver

300,749 gold equivalent ounces at the high end of revised guidance of 289,000-303,000 ounces

25.0 million silver equivalent ounces

§ 2023 all-in sustaining costs expected to meet revised guidance of $1,490-1,580 per gold equivalent ounce ($18.0-19.0 per silver equivalent ounce)

Project highlights

§  Mara Rosa project is 99.8% complete with first gold pour expected in February

On time and on budget

5 million hours completed on the project without any loss time accidents

Financial position

§ Total cash of approximately $89 million as at 31 December 2023 ($144 million as at 31 December 2022)

§ Net debt of approximately $252 million as at 31 December 2022 (net debt of $175 million as at 31 December 2022)

§ Current Net Debt/LTM EBITDA of approximately 0.97x as at 31 December 2023, improved from 1.12x in September 2023

§ Zero cost collar executed for 100,000oz of 2024 gold production from Inmaculada an average floor of $2,000/oz and an average cap of $2,252/oz

2023 ESG highlights

§ Lost Time Injury Frequency Rate of 0.99 (FY 2022: 1.37)[2]

§ Accident Severity Index of 37 (FY 2022: 93)[3]

§ Water Consumption of 163 lt/person/day (FY 2022: 171 lt/person/day)

§ Domestic waste generation of 0.93 kg/person/day (FY 2022: 1.05 kg/person/day)

§ ECO score of 5.76 out of 6 (FY 2022: 5.27)[4]

Growth in 2024

§ New Mara Rosa mine set to produce 83,000-93,000 ounces of gold at AISC of $1,090-$1,120 per ounce

§ Overall production target:

343,000-360,000 gold equivalent ounces

§ All-in sustaining costs target:

$1,510-$1,550 per gold equivalent ounce

§ Total sustaining and development capital expenditure expected to be approximately $171-178 million

________________________________________________________________________________________

 

A conference call will be held at 2.00pm (London time) on Wednesday 24 January 2024 for analysts and investors. 

Dial in details as follows:

UK Toll-Free: 0808 109 0700

International Dial in: +44 (0)330 551 0200

US Toll-Free: 866-580-3963

Canada Toll-Free: 866-378-3566

Password: Hochschild Mining

A recording of the conference call will be available on demand on the Company's website: www.hochschildmining.com

________________________________________________________________________________________

 



 

Overview

In Q4 2023, Hochschild Mining PLC (HOC.LN) (OTCMKTS: $HCHDF) ("Hochschild" or "the Company") delivered attributable production of 82,251 gold equivalent ounces or 6.8 million silver equivalent ounces, slightly stronger than Q3. Overall 2023 attributable production was 300,749 gold equivalent ounces or 25.0 million silver equivalent ounces. The result was at the upper end of revised guidance, due to a better-than-forecast performance at Inmaculada.

 

The Company reiterates that its all-in sustaining cost for 2023 is expected to be in line with the revised guidance of between $1,490-1,580 per gold equivalent ounce ($18.0-19.0 per silver equivalent ounce)

 

TOTAL GROUP PRODUCTION

 

Q4 2023

Q3 2023

Q4 2022

12 mths 
2023

12 mths 
2022

Silver production (koz)

3,086

3,205

3,632

11,683

13,596

Gold production (koz)

64.41

60.81

68.11

225.77

244.63

Total silver equivalent (koz)

8,432

8,252

9,285

30,423

33,900

Total gold equivalent (koz)

101.59

99.42

111.87

366.54

408.43

Silver sold (koz)

3,231

2,911

3,596

11,567

13,536

Gold sold (koz)

68.14

53.93

67.40

221.86

242.89

Total production includes 100% of all production, including production attributable to Hochschild's joint venture partner at San Jose.

                                     

ATTRIBUTABLE GROUP PRODUCTION

 

Q4 2023

Q3 2023

Q4 2022

12 mths 
2023

12 mths 
2022

Silver production (koz)

2,450

2,624

2,931

9,517

11,003

Gold production (koz)

52.73

50.00

56.94

186.09

206.01

Silver equivalent (koz)

6,827

6,774

7,657

24,962

28,102

Gold equivalent (koz)

82.25

81.62

92.26

300.75

338.57

Attributable production includes 100% of all production from Inmaculada, Pallancata and 51% from San Jose.

 

Production

Inmaculada

Product

Q4 2023

Q3 2023

Q4 2022

12 mths 
2023

12 mths 
2022

Ore production (tonnes treated)

301,127

300,076

323,870

1,137,109

1,329,177

Average grade silver (g/t)

186

166

182

177

156

Average grade gold (g/t)

4.63

3.97

4.29

4.09

3.81

Silver produced (koz)

1,500

1,442

1,602

5,515

5,936

Gold produced (koz)

        39.35

         36.19

        42.36

137.40

154.85

Silver equivalent (koz)

         4,766

        4,446

          5,118

16,919

18,788

Gold equivalent (koz)

         57.42

         53.57

         61.66

203.85

226.36

Silver sold (koz)

1,587

1,340

1,599

5,488

5,918

Gold sold (koz)

41.95

33.32

42.15

136.66

154.93

 

Fourth quarter production at Inmaculada was 39,354 ounces of gold and 1.5 million ounces of silver, which amounts to a gold equivalent output of 57,425 ounces, with higher tonnage and grades from newer mining areas. Overall, in 2023, Inmaculada has delivered gold equivalent production of 203,849 ounces (2022: 226,363 ounces), slightly above the revised forecast published in August.


Pallancata

Product

Q4 2023

Q3 2023

Q4 2022

12 mths 
2023

12 mths 
2022

Ore production (tonnes treated)

51,738

122,681

155,530

414,044

559,799

Average grade silver (g/t)

             199

              171

             139

155

151

Average grade gold (g/t)

0.84

0.73

0.68

0.64

0.69

Silver produced (koz)

288

578

600

1,746

2,368

Gold produced (koz)

1.22

2.56

2.95

7.39

10.98

Silver equivalent (koz)

           390

             791

            845

2,359

3,279

Gold equivalent (koz)

           4.70

           9.53

          10.18

28.43

39.50

Silver sold (koz)

285

576

561

1,785

2,315

Gold sold (koz)

1.20

2.57

2.80

7.52

10.76

 

In Q4, Pallancata produced 0.3 million ounces of silver and 1,224 ounces of gold bringing the silver equivalent total to 0.4 million, with the mine still operating a little later in the quarter than expected. Overall, in 2023, Pallancata produced 2.4 million silver equivalent ounces (2022: 3.3 million ounces) slightly above the revised forecast (2.0 -2.2 million ounces). In Q4, as previously announced, Pallancata suspended operations and was placed on care and maintenance.

 

The process of amending Pallancata's environmental impact assessment ("Third MEIA") to incorporate the Royropata discovery into the permitted area formally began in December and is advancing on schedule. Feasibility engineering is over 90% completed and environmental and social baseline studies will be conducted during 2024.  

 

San Jose (the Company has a 51% interest in San Jose)

Product

Q4 2023

Q3 2023

Q4 2022

12 mths 
2023

12 mths 
2022

Ore production (tonnes treated)

154,308

152,729

152,692

579,100

507,189

Average grade silver (g/t)

297

271

332

270

369

Average grade gold (g/t)

5.51

5.16

5.38

5.03

5.55

Silver produced (koz)

1,297

1,184

1,430

4,422

5,292

Gold produced (koz)

23.84

22.05

22.80

80.99

78.80

Silver equivalent (koz)

         3,276

3,015

        3,323

11,144

11,833

Gold equivalent (koz)

         39.47

36.32

       40.03

134.26

142.57

Silver sold (koz)

1,339

994

1,435

4,274

5,303

Gold sold (koz)

24.54

18.03

22.46

77.23

77.20

 

The San Jose mine experienced lower than expected grades, resulting in production of 1.3 million ounces of silver and 22,836 ounces of gold in the quarter, which represents 3.3 million silver equivalent ounces. This amounts to a 2023 total production of 11.1 million silver equivalent ounces (2022: 11.8 million ounces).

 

Average realisable prices and sales

Average realisable precious metal prices in Q4 2023 (which are reported before the deduction of commercial discounts) were $2,036/ounce for gold and $23.7/ounce for silver (Q4 2022: $1,767/ounce for gold and $25.8/ounce for silver).

 

For 2023 as a whole, average realisable precious metal prices were $1,974/ounce for gold and $23.7/ounce for silver (2022: $1,791/ounce for gold and $23.3/ounce for silver).

 

Advanced Project: Mara Rosa

The Mara Rosa project is progressing on schedule and budget with total project progress at 99.8%. The Company continues to expect first gold pour during the month of February and commercial production in the second quarter.

 

Health and Safety

Proactive corporate safety indicators are being monitored to ensure optimal working conditions for all personnel and the project has completed approximately five million hours without loss time accident. Frequency and severity indices for 2023 were 0.54 and 2, respectively, both better than corporate goals

Procurement

 Main plant reagents and materials, including cyanide, balls for the mills, lime and activated carbon have been purchased and deliveries are on track to meet the start of operations.

 

Mine and Pre-Stripping

Total pre-stripping volume was 2,091 kt of which there is approximately 136.5 kt to guarantee availability of mineral for the ramp-up and operation. Waste dumps and ore stockpiles are complete and being used.

 

Processing plant

The crushing and screening areas were commissioned during Q4 whilst commissioning began of the thickener and ball mill.  Full project commissioning and the beginning of the project's ramp-up is expected during the first quarter.

 

Quality control teams are consistently monitoring all critical project progress such assembly of metallic structures, equipment, piping, welding and commissioning activities.

 

Infrastructure

Construction of the dry stack was completed in December 2023 and the Pequi water reservoir is fully operational and filled to 95% capacity with the water required for 2024 operations.

 

The Administrative buildings are fully operational including offices, cafeteria, first aid and nursery areas.

 

Permitting & Sustainability

During Q4, Mara Rosa received authorisation for commissioning of the wet circuit with the dry circuit already permitted.  During early December, the project was visited by officials from EPA-Goias to assess the issuance of the Operating License which is expected to occur in February.

 

The Company organised three festivities to celebrate Children's Day in Mara Rosa and Amaralina with over 3,100 participants whilst on 2 November, a meeting with the local communities from both towns was held with the objective of updating them on project progress and strengthening local relationships and dialogue.

 

Brownfield exploration

Inmaculada

In Q4 2023, the Company performed 900m of potential drilling, intercepting two new structures, Nicolas and Andrea, which will be further investigated in this quarter.

 

Vein

Results (potential drilling)

Nicolas

IMS23-207: 1.8m @ 27.0g/t Au & 5,768g/t Ag

Andrea

IMS23-207: 3.3m @ 19.4g/t Au & 79g/t Ag

Saly

IMS23-207: 2.2m @ 3.2g/t Au & 90g/t Ag

 

San Jose

At San Jose, the brownfield team carried out 906m of potential drilling and 4,420m of resource drilling in the Suspiro, Sigmoid Molle, Guadaluoe veins with the key vein expected to be the Suspira quartz sulphide vein which has high silver grades.

 

Vein

Results (potential/resource drilling)

Suspira

SJD-2737: 1.2m @ 17.4g/t Au & 2,477g/t Ag

Tensiona EW

SJM-647: 1.0m @ 7.7g/t Au & 938g/t Ag

RML861V

SJD-2728: 1.1m @ 6.9g/t Au & 615g/t Ag

Sig Molle

SJM-647: 2.8m @ 5.7g/t Au & 656g/t Ag

RML861w

SJD-2731: 1.3m @ 5.5g/t Au & 8g/t Ag

 

The plan for the first quarter is to perform 1,500m of potential drilling at San Jose in the Telken North and Cerro Saavedra areas.

 

Financial position

Total cash was approximately $89 million as at 31 December 2023, resulting in net debt of approximately $252 million.

 

To ensure an ongoing level of cash flow stability from Inmaculada, the Company has secured a zero-cost collar with JPMorgan for 100,000 ounces of our 2024 gold production with an average floor at $2,000/oz and an average cap at $2,252/oz.



 

 

____________________________________________________________________________________

 

Enquiries:

 

Hochschild Mining PLC

Charles Gordon                                                                                                                                                                             +44 (0)20 3709 3264

Head of Investor Relations

 

Hudson Sandler

Charlie Jack                                                                                                                                                                                  +44 (0)207 796 4133

Public Relations

_____________________________________________________________________________________

 

About Hochschild Mining PLC

Hochschild Mining PLC is a leading precious metals company listed on the London Stock Exchange (HOCM.L / HOC LN) with a primary focus on the exploration, mining, processing and sale of silver and gold. Hochschild has over fifty years' experience in the mining of precious metal epithermal vein deposits and currently operates three underground epithermal vein mines, two located in southern Peru and one in southern Argentina. Hochschild also owns the Mara Rosa Advanced Project in Brazil as well as numerous long-term projects throughout the Americas. _____________________________________________________________________________________

 

Forward looking statements

This announcement may contain forward looking statements. By their nature, forward looking statements involve risks and uncertainties because they relate to events and depend on circumstances that will or may occur in the future. Actual results, performance or achievements of Hochschild Mining PLC may, for various reasons, be materially different from any future results, performance or achievements expressed or implied by such forward looking statements.

 

The forward looking statements reflect knowledge and information available at the date of preparation of this announcement. Except as required by the Listing Rules and applicable law, the Board of Hochschild Mining PLC does not undertake any obligation to update or change any forward looking statements to reflect events occurring after the date of this announcement. Nothing in this announcement should be construed as a profit forecast.

 

This announcement contains information which prior to its release could be considered inside information.

LEI: 549300JK10TVQ3CCJQ89

 

- ends -



[1]2023 equivalent figures calculated using the Company gold/silver ratio of 83x. All 2024 forecasts assume the average gold/silver ratio for 2023 also at 83x

[2]Calculated as total number of accidents per million labour hours

[3]Calculated as total number of days lost per million labour hours.

[4]The ECO Score is an internally designed Key Performance Indicator measuring environmental performance in one number and encompassing numerous fronts including management of waste water, outcome of regulatory inspections and sound environmental practices relating to water consumption and the recycling of materials.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
TSTKXLFLZFLZBBE