NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION, IN WHOLE OR IN PART, DIRECTLY OR INDIRECTLY, IN OR INTO OR FROM THE UNITED STATES, AUSTRALIA, CANADA, JAPAN, THE REPUBLIC OF SOUTH AFRICA OR ANY OTHER JURISDICTION WHERE IT IS UNLAWFUL TO DISTRIBUTE THIS ANNOUNCEMENT.
URA Holdings plc
("URA" or the "Company")
Commission of Processing and Sorting Plants begins
URA Holdings plc (LSE: URAH), the gemstone mining company currently focused on the restart of production at the Gravelotte Emerald Mine ("GEM"), is pleased to announce that its operations have now entered the commissioning phase, targeting first production before the end of April 2024.
Highlights
· Practical completion of the priority systems at the Gravelottle processing and sorting plant, allowing the commissioning phase to commence.
· Phased Emerald production expected to commence before the end of April 2024
· Sufficient ore feed tonnes are now readily accessible on the run-of-mine (ROM) pads for both commissioning and first production with a total available ROM stockpile now exceeding 3,000 tonnes
· Mechanical equipment pre-operational testing is also currently in progress
· Technical Team from the manufactures of the optical sorter (Angelon Electronics Co Ltd) are on site actively working to achieving final assembly and commissioning of the optical sorter on schedule
Bernard Olivier, CEO of URA, commented: "We are pleased to report that we are on track to first production before the end of April and the start of commission of the processing and sorting plant is a significant final step in achieving this objective. Operational readiness and the transition to daily operations is a key part of this phase as we look not only to first emerald production but also towards ramping up production with a view to achieve first sales from the historic emerald mine for over 20 years."
Figure 1. The commissioning of the processing plant in progress.
Figure 2. Angelon technical expert busy with the commissioning of the optical sorter.
Enquiries:
URA Holdings plc Chief Executive Officer Bernard Olivier
Director Peter Redmond
Chief Operating Officer
| +44 (0)746 368 6497
|
Peterhouse Capital Limited Joint Corporate Broker Lucy Williams Duncan Vasey
Capital Plus Partners Joint Corporate Broker Keith Swann Jon Critchley | +44 (0)20 7469 0930
+44 (0)203 821 6169 +44 (0)203 821 6168
|
CMC Markets Joint Corporate Broker Douglas Crippen |
+44 (0)20 3003 8632 |
About URA Holdings Plc
URA is focused on restarting the Gravelotte Emerald Mine. URA Holdings is committed to sustainable and efficient mining practices, utilising modern technology to revive one of the world's historically significant emerald mines.
For more information about URA Holdings Plc, including investor relations and corporate news, please visit our website at www.uraholdingsplc.co.uk or follow us through our social media channel:
X(formally known as Twitter): @ura_plc
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.