RNS Number : 2950B
Kistos Holdings PLC
21 August 2024
 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF ARTICLE 7 OF REGULATION 2014/596/EU WHICH IS PART OF DOMESTIC UK LAW PURSUANT TO THE MARKET ABUSE (AMENDMENT) (EU EXIT) REGULATIONS (SI 2019/310) (UK MAR). UPON THE PUBLICATION OF THIS ANNOUNCEMENT, THIS INSIDE INFORMATION (AS DEFINED IN UK MAR) IS NOW CONSIDERED TO BE IN THE PUBLIC DOMAIN.

 

21 August 2024

Home - Kistos

 

Kistos Holdings plc

 

("Kistos" or "the Company")

 

Balder X project update - Kistos shareholders protected from any delay

 

Kistos (LON: KIST), notes that Var Energi ("Var" or "the Operator"), released an update for the Balder X project this morning, in which Kistos Energy (Norway) AS ("KENAS") has a 10% interest. Var reported that the target production start date has been moved to the second quarter 2025.

 

When Kistos acquired Mime Petroleum this scenario was envisaged. In the deal structuring with the bond holders (who effectively controlled MIME at the time) we protected Kistos from such a delay and cost increase by the provision of the $45 million Hybrid Bond. This $45 million is structured such that if 500,000 bbls (gross) isn't lifted from the Jotun FPSO before the 31st May 2025 then the full $45 million is not payable. Therefore, we as a board are confident that there will be no adverse impact from the delay. It is likely that the effect of the delay on Capex will be significantly less than the positive effects of the Hybrid Bond not being paid in full.

 

In reaching the decision to delay Balder X, a key consideration was to limit as much as possible the carryover of work on the Jotun FPSO into the offshore installation and start-up phase. With all development wells completed and all subsea production systems installed, the plan now is to complete the vessel fully onshore.

 

The operator has reviewed its cost estimate for the project to reflect sail-away of the Jotun FPSO in the spring of 2025. The revised CAPEX forecast represents an increase of approximately US$400 million gross pre-tax (approximately $40 million net to Kistos pre-tax, of which $8.8 million is the approximate post-tax impact) of which 75% is expected to be incurred in 2025.

 

As announced by Var this morning, Balder X, will secure production from the Balder Area beyond 2045. It will unlock gross proved plus probable (2P) reserves of around 150 mmboe (gross) and peak output of about 90 kboepd (gross).

 

Importantly, as an area host, the Jotun FPSO will enable future growth opportunities. Balder Phase V is being progressed, including the drilling of six production wells to utilise the remaining subsea template well slots to capture gross 2P reserves of over 30 mmboe. Drilling of these wells will commence in the first half of 2025 and be completed in 2026.

 

In addition, the Balder Phase VI project is being matured, to add new subsea facilities and wells, with an investment decision expected in the first half of 2025. Var notes there remains significant resource upside in the area and further exploration drilling and tie-back development phases are being planned.

 

 

Kistos Holdings plc

Andrew Austin

 

via Hawthorn Advisors

Panmure Liberum (NOMAD, Joint Broker)

James Sinclair-Ford / Dougie McLeod / Mark Murphy

 

Tel: 0207 886 2500

Berenberg (Joint Broker)

Matthew Armitt / Ciaran Walsh

 

Tel: 0203 207 7800

Hawthorn Advisors (Public Relations Advisor)

Henry Lerwill / Simon Woods

 

Tel: 0203 745 4960

Camarco (Public Relations Advisor)

Billy Clegg

Tel: 0203 757 4983

 

Notes to editors

 

Kistos Holdings plc was established to acquire and manage companies in the energy sector engaging in the energy transition trend. The Company has undertaken a series of transactions including the acquisition of a portfolio of highly cash generative natural gas production assets in the Netherlands from Tulip Oil Netherlands B.V. in 2021. This was followed in July 2022, with the acquisition of a 20% interest in the Greater Laggan Area (GLA) from TotalEnergies, which includes four producing gas fields and a development project. In May 2023, Kistos completed the acquisition of Mime Petroleum A.S. adding 24 MMboe of 2P reserves and significant production. In April 2024, Kistos completed the acquisition of UK gas storage assets, which due to the fast cycle nature of the facility, can deliver up to 11% of the UK's flexible daily gas capacity if called upon.

 

Kistos is a low-carbon intensity energy producer with Estimated Scope 1 CO2e emissions from our operated activities offshore Netherlands of less than 0.01 kg/boe in 2023 (excluding necessary flaring during drilling campaigns).

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDQKDBPKBKDBFB