THIRD QUARTER PRODUCTION REPORT

FOR THE THREE MONTHS ENDED 30 SEPTEMBER 2024

 

Octavio Alvídrez, Chief Executive Officer, said:

 

"We have delivered another solid quarter, in line with the consistent operating performance we have achieved all year. Our full year guidance set out in January remains unchanged. In silver, Saucito and San Julián Veins have performed very well, helping to offset slightly lower output at Fresnillo. In gold, we have delivered a rapid recovery at Herradura after the mine plan was impacted by heavy rains earlier in the year, with gold production increasing 40% quarter on quarter, and at Ciénega we have delivered a strong increase in gold output year to date, testament to the outstanding work of the team on the ground. This operational consistency gives us confidence as we enter the final quarter. As we look further ahead, our priorities are unchanged. Safety is our key focus while we continue to drive efficiencies and performance across our mine sites."

 

HIGHLIGHTS

 

Silver

 

·    Quarterly attributable silver production of 14.4 moz (including Silverstream) down 1.5% vs. 2Q24 due to the lower ore grade and decrease in volume of ore processed at San Julián DOB as it approaches the end of its life and lower ore grade at Ciénega. This was partly mitigated by the higher ore grade at Saucito and increased volume of ore processed at San Julián Veins.

 

·    Quarterly attributable and YTD silver production (including Silverstream) increased 2.4% and 1.2% vs. 3Q23 and YTD23 respectively, mainly due to the higher ore grades and volume of ore processed at Saucito and San Julián Veins. This was partly offset by the decrease in production at San Julián DOB, lower ore grades and volume of ore processed at Fresnillo, and lower contribution from the Silverstream.

 

Gold

 

·   

 

·    Quarterly attributable gold production increased 18.2% vs. 3Q23 primarily due to the increased volume of ore processed at Herradura and, to lesser extent, higher ore grade at Fresnillo and San Julián Veins and increased volume of ore processed and higher ore grade at Saucito. This was partly offset by the mine closure plan at Noche Buena.

 

·    Year to date gold production of 427.6 koz, down 6.6% vs. YTD23 mainly due to lower ore grade and recovery rate at Herradura and the mine closure plan at Noche Buena. This was partly mitigated by higher ore grade at Fresnillo and, to a lesser extent, higher ore grade and volume of ore processed at San Julián Veins and Ciénega.

 

 

By-Products

 

•    

 

•    

 

•    

•    

 

•     Year to date attributable by-product lead and zinc production up 18.1% and 11.2% vs. YTD23 respectively, mainly due to increased volume of ore processed at Juanicipio and Saucito and higher ore grades at Fresnillo and Juanicipio, partly offset by the decreased contribution from San Julián DOB.

 

 


3Q24

2Q24

% Change

3Q23

% Change

YTD24

YTD23

% Change

Silver (koz)

13,886

14,038

(1.1)

13,434

3.4

41,041

39,905

2.8

Silverstream (koz)

552

617

(10.5)

670

(17.6)

1,566

2,216

(29.3)

Total Silver (koz)

14,439

14,655

(1.5)

14,104

2.4

42,607

42,121

1.2

Gold (oz)

156,759

130,025

20.6

132,627

18.2

427,631

458,042

(6.6)

Lead (t)

17,707

16,906

4.7

14,575

21.5

49,536

41,938

18.1

Zinc (t)

32,297

29,240

10.5

29,073

11.1

87,695

78,861

11.2

 

SAFETY PERFORMANCE

 

We are deeply saddened to report a fatal accident during the third quarter at the Ciénega mine. We continue working towards identifying preventive measures, focusing on training and maintaining stringent adherence to our safety policies to provide a safer environment for our workforce. We remain committed to meeting our Zero Fatalities target by instilling a strong safety culture through our operations.

 

                                        

2024 OUTLOOK

 

Our 2024 outlook remains in line with previous guidance:

·    Attributable silver production expected to be in the range of 55.0 to 62.0 moz (including Silverstream).

·    Attributable gold production expected to be in the range of 580 to 630 koz.

Expressed in silver equivalent ounces[1], total production is expected to be 101-112 million ounces.

 

For further information, please visit our website www.fresnilloplc.com or contact:

 

FRESNILLO PLC     

London Office                        

Gabriela Mayor, Head of Investor Relations

Mark Mochalski

 

Tel: +44 (0)20 7399 2470

Mexico City Office

Ana Belem Zárate

Tel: +52 55 52 79 3206

Peter Ogden

 

 

MINING OPERATIONS

 

FRESNILLO MINE PRODUCTION

 


3Q24

2Q24

% Change

3Q23

% Change

 YTD24

YTD23

% Change

Ore Processed (t)

578,523

589,602

(1.9)

673,233

(14.1)

1,790,515

2,009,374

(10.9)










Production









Silver (koz)

2,590

2,583

0.3

3,201

(19.1)

7,849

9,990

(21.4)

Gold (oz)

14,396

13,309

8.2

9,013

59.7

37,551

28,760

30.6

Lead (t)

7,526

6,433

17.0

5,175

45.4

20,150

16,147

24.8

Zinc (t)

14,365

11,260

27.6

12,003

19.7

37,293

34,793

7.2










Ore Grades









Silver (g/t)

155

152

2.0

166

(6.6)

152

173

(12.1)

Gold (g/t)

1.04

0.95

9.5

0.59

76.3

0.88

0.62

41.9

Lead (%)

1.50

1.27

18.1

0.90

66.7

1.31

0.94

39.4

Zinc (%)

3.32

2.61

27.2

2.33

42.5

2.83

2.29

23.6

 

Quarterly silver production was in line with 2Q24, as the higher ore grade was offset by the slight decline in ore processed.

 

Quarterly silver production decreased 19.1% vs. 3Q23, due to the decrease in volume of ore processed and lower ore grade mainly due to: i) the lower availability of ore to feed the beneficiation plant as ore was hauled via ramps while the two sections of the deepened San Carlos shaft were connected; ii) narrower veins; and iii) changes to the mine plan as cut-off grades in several areas were adjusted to reflect the higher metal prices.

 

Year to date silver production decreased 21.4% vs. YTD23 primarily driven by the decreased volume of ore processed and the lower ore grade due to a higher proportion of volumes extracted from western areas of the mine with lower silver ore grade, but higher gold and base metal content, in addition to narrower veins and changes to the mine plan as explained above.

 

Mine development rates increased to an average of 3,296m per month in 3Q24 (2Q24: 3,191m per month).

 

Quarterly and year to date gold production increased vs. all comparative periods driven by the higher ore grade, partly offset by the decreased volume of ore processed.

 

The silver ore grade in 2024 is expected to be in the range of 160 to 180 g/t, while the gold ore grade is estimated to be between 0.70 to 0.90 g/t.

 

 

 

SAUCITO MINE PRODUCTION

 


3Q24

2Q24

% Change

3Q23

% Change

YTD 24

 YTD 23

% Change

Ore Processed (t)

590,362

599,601

(1.5)

552,872

6.8

1,764,932

1,587,793

11.2










Production









Silver (koz)

3,697

3,577

3.4

2,892

27.8

10,507

8,703

20.7

Gold (oz)

19,856

18,314

8.4

15,427

28.7

57,513

55,508

3.6

Lead (t)

5,738

5,658

1.4

4,973

15.4

16,304

13,224

23.3

Zinc (t)

9,280

8,909

4.2

9,663

(4.0)

24,884

22,656

9.8










Ore Grades









Silver (g/t)

219

208

5.3

183

19.7

208

192

8.3

Gold (g/t)

1.35

1.23

9.8

1.14

18.4

1.31

1.39

(5.8)

Lead (%)

1.13

1.10

2.7

1.06

6.6

1.08

0.99

9.1

Zinc (%)

1.99

1.92

3.6

2.22

(10.4)

1.81

1.85

(2.2)

 

Quarterly silver production increased 3.4% vs. 2Q24 due to higher silver ore grade, partly offset by a decline in volume of ore processed.

 

Quarterly and year to date silver production increased 27.8% and 20.7% vs. 3Q23 and YTD23 respectively, primarily due to the higher ore grade, and increased volume of ore processed driven by the increased productivity and availability of equipment, enabling a stricter adherence to the mine plan.

 

Quarterly by-product gold production increased 8.4% vs. 2Q24 mainly due to higher ore grade, partly offset by lower volume of ore processed quarter-on-quarter.

 

Quarterly by-product gold production increased 28.7% vs 3Q23 mainly due to the increased volume of ore processed and higher ore grade.

 

YTD gold production increased 3.6% vs YTD23 as a result of the increase in volume of ore processed, partly offset by the decrease in ore grade.

 

Mine development rates decreased to an average of 2,500m per month in 3Q24 (2Q24: 2,867m per month) primarily due to additional ventilation and pumping needed in certain areas. The progress of the measures to improve these services and increase the timely preparation of the areas to be developed is being closely monitored and development rates are expected to increase in the coming quarters.

 

The silver ore grade for 2024 is expected to be in the range of 200-220 g/t, while the gold grade is estimated to be between 1.10-1.30 g/t.

 

PYRITES PLANT

 


3Q24*

2Q24*

% Change

3Q23*

% Change

YTD24*

YTD23*

% Change

Pyrite Concentrates Processed (t)

39,845

40,077

(0.6)

46,934

(15.1)

116,266

114,177

1.8










Production









Silver (koz)

527

490

7.6

225

134.2

1,374

532

158.3

Gold (oz)

790

711

11.1

597

32.3

2,129

1,361

56.4










Ore Grades









Silver (g/t)

564

576

(2.1)

220

156.4

547

212

158.0

Gold (g/t)

2.14

2.23

(4.0)

1.46

46.6

2.17

1.53

41.8

*Includes concentrates of Fe from Saucito and Fresnillo.

 

 

 

 

 

CIÉNEGA MINE PRODUCTION

 


3Q24

2Q24

% Change

3Q23

% Change

YTD24

YTD23

% Change

Ore Processed (t)

272,133

257,861

5.5

270,531

0.6

791,676

771,931

2.6










Production









Gold (oz)

8,887

9,981

(11.0)

9,314

(4.6)

29,556

26,748

10.5

Silver (koz)

1,218

1,379

(11.7)

1,131

7.7

3,799

3,122

21.7

Lead (t)

669

982

(31.9)

683

(2.0)

2,303

2,187

5.3

Zinc (t)

632

812

(22.2)

906

(30.2)

2,275

2,827

(19.5)










Ore Grades









Gold (g/t)

1.14

1.31

(13.0)

1.16

(1.7)

1.27

1.17

8.5

Silver (g/t)

163

192

(15.1)

151

7.9

174

146

19.2

Lead (%)

0.39

0.57

(31.6)

0.42

(7.1)

0.45

0.45

0.0

Zinc (%)

0.44

0.58

(24.1)

0.64

(31.3)

0.54

0.69

(21.7)

Quarterly gold and silver production decreased 11.0% and 11.7% vs. 2Q24 respectively, mainly due to the lower ore grade, partly compensated for by the increase in volume of ore processed in accordance with the mine plan.

Quarterly gold production decreased 4.6% vs. 3Q23 primarily due to lower ore grade and decrease in recovery rate.

Quarterly silver production increased 7.7% vs. 3Q23 mainly due to the higher ore grade at the Jessica Transversal and Taspana Sur areas.

Year to date gold and silver production increased 10.5% and 21.7% vs. YTD23 due to the higher ore grade as mentioned above and an increased volume of ore processed driven by the contribution from the Taspana area, and the timely preparation of stopes.

The gold and silver ore grades for 2024 are estimated to be in the ranges of 1.1-1.3 g/t and 160-180 g/t respectively.

 

SAN JULIÁN MINE PRODUCTION

 


3Q24

2Q24

% Change

3Q23

% Change

YTD24

YTD23

% Change

Ore Processed Veins (t)

314,786

301,643

4.4

292,391

7.7

907,432

850,648

6.7

Ore Processed DOB (t)

435,804

458,793

(5.0)

498,607

(12.6)

1,396,031

1,548,765

(9.9)

 









Total production at San Julián









Gold (oz)

12,412

12,846

(3.4)

11,161

11.2

37,839

33,453

13.1

Silver (koz)

2,997

3,117

(3.8)

3,185

(5.9)

9,154

10,193

(10.2)

 









Production Veins









Gold (oz)

11,914

12,353

(3.6)

10,428

14.3

36,240

30,892

17.3

Silver (koz)

2,095

2,022

3.6

1,359

54.2

6,156

3,839

60.4










Production DOB









Gold (oz)

498

493

1.0

733

(32.1)

1,600

2,561

(37.5)

Silver (koz)

902

1,096

(17.7)

1,826

(50.6)

2,998

6,354

(52.8)

Lead (t)

1,068

1,303

(18.0)

1,595

(33.0)

3,332

5,511

(39.5)

Zinc (t)

3,763

3,472

8.4

3,273

15.0

10,476

11,049

(5.2)










Ore Grades Veins









Gold (g/t)

1.24

1.34

(7.5)

1.18

5.1

1.31

1.19

10.1

Silver (g/t)

226

228

(0.9)

158

43.0

231

154

50.0










Ore Grades DOB









Gold (g/t)

0.06

0.05

20.0

0.08

(25.0)

0.06

0.08

(25.0)

Silver (g/t)

77

88

(12.5)

134

(42.5)

80

148

(45.9)

Lead (%)

0.34

0.38

(10.5)

0.42

(19.0)

0.32

0.46

(30.4)

Zinc (%)

1.14

1.03

10.7

0.90

26.7

1.01

0.96

5.2

 

SAN JULIÁN VEINS

Quarterly silver production increased 3.6% vs. 2Q24, mainly due to the higher volume of ore processed driven by the timely preparation of stopes, partly offset by the lower ore grade.

Quarterly gold production decreased 3.6% vs. 2Q24 due to the lower ore grade, mitigated by the increase in volume of ore processed.

Quarterly and year to date silver and gold production increased vs. 3Q23 and YTD23 respectively, mainly due to the higher ore grades at the San Antonio, La Dura, Eliza and Última Tierra areas, together with improved dilution control as wider veins were mined. The additional preparation of stopes and the implementation of an operational plant optimisation programme increased the processing capacity, hence increasing silver and gold production during these periods.

Silver and gold ore grades are expected to be in the ranges of 200-230 g/t and 1.20-1.40 g/t, respectively.

 

SAN JULIÁN DISSEMINATED ORE BODY (DOB)

Quarterly and year to date silver production decreased vs. all comparative periods as a result of the gradual decrease in production at this mine and the unforeseen geotechnical behaviour of the ore body as it approaches its final stage, with mining activities expected to conclude in 4Q24.

We expect the 2024 silver ore grade to be around 80 g/t.

 

HERRADURA TOTAL MINE PRODUCTION

 


3Q24

2Q24

% Change

3Q23

% Change

YTD24

YTD23

% Change

Ore Processed (t)

6,257,754

5,756,109

8.7

3,983,615

57.1

16,709,393

15,689,168

6.5

Total Volume Hauled (t)

26,148,467

27,093,586

(3.5)

24,462,202

7.0

75,382,829

75,131,727

0.3










Production









Gold (oz)

89,030

63,628

39.9

72,184

23.3

230,716

262,053

(12.0)

Silver (koz)

119

100

19.0

120

(0.8)

338

464

(27.2)










Ore Grades









Gold (g/t)

0.70

0.59

18.6

0.73

(4.1)

0.65

0.74

(12.2)

Silver (g/t)

1.10

1.06

3.8

1.51

(27.2)

1.15

1.54

(25.3)

 

Quarterly gold production increased 39.9% vs. 2Q24 mainly due to higher ore grade, improved recovery rate and increased volume of ore processed as mine preparation was intensified and access to higher grade oxidised ore areas was regained. This trend is expected to continue into 4Q24, thus further compensating for the lower production in 2Q24.

Quarterly gold production increased 23.3% vs. 3Q23 as a result of the higher volume of ore processed due to the electrical fault in 3Q23, partly offset by the lower ore grade and recovery rates.

Year to date gold production grade as a result of the change in the mine sequence in 1H24 and decreased recovery rate. This was partly mitigated by the higher volume of ore processed.

The average gold ore grade in 2024 is expected to be in the

 

NOCHE BUENA

 

5,339 ounces of gold were recovered from the leaching pads at Noche Buena in 3Q24. Year to date gold production totalled 15,534 ounces. As previously announced, mining activities concluded in May 2023, and the closure plan continues as expected.

 

 

JUANICIPIO - ATTRIBUTABLE

 


3Q24

2Q24

% Change

3Q23*

% Change

YTD 24

YTD 23*

% Change

Ore Processed (t)

186,082

188,492

(1.3)

180,460

3.1

556,957

516,315

7.9

 









Production









Silver (koz)

2,736

2,791

(2.0)

2,678

2.2

8,016

6,892

16.3

Gold (oz)

6,049

5,185

16.7

5,289

14.4

16,793

14,640

14.7

Lead (t)

2,707

2,529

7.0

2,150

25.9

7,447

4,868

53.0

Zinc (t)

4,257

4,788

(11.1)

3,227

31.9

12,767

7,536

69.4










Ore Grades









Silver (g/t)

481

498

(3.4)

523

(8.0)

485

474

2.3

Gold (g/t)

1.32

1.20

10.0

1.32

0.0

1.28

1.23

4.1

Lead (%)

1.58

1.56

1.3

1.33

18.8

1.50

1.07

40.2

Zinc (%)

2.83

2.99

(5.4)

2.25

25.8

2.77

1.92

44.3

* Includes ore processed from initial tests during the commissioning of the Juanicipio plant and ore processed at the Fresnillo and Saucito beneficiation plants.

 

Attributable quarterly silver production decreased 2.0% vs. 2Q24 driven by the lower ore grade and decreased volume of ore processed both in accordance with the mine plan. Attributable quarterly gold production increased 16.7% vs. 2Q24 mainly due to higher ore grade and improved recovery rate.

 

Attributable quarterly silver and gold production increased 2.2% and 14.4% vs. 3Q23 respectively, due to higher recovery rate and increased volume of ore processed as the beneficiation plant is now operating at full capacity and the flotation process has been optimised.

Year to date silver and gold production increased significantly vs. YTD23 as commissioning of the flotation plant concluded in 1Q23 and ramp up of the beneficiation plant took place in 2Q23 and 3Q23.

 

 

SILVERSTREAM

 

 

ABOUT FRESNILLO PLC

Fresnillo plc is the world's largest primary silver producer and Mexico's largest gold producer, listed on the London and Mexican Stock Exchanges under the symbol FRES.

Fresnillo plc has eight operating mines, all of them in Mexico - Fresnillo, Saucito, Juanicipio, Ciénega, Herradura, Soledad-Dipolos1, Noche Buena and San Julián (Veins and Disseminated Ore Body) and four advanced exploration projects - Orisyvo, Rodeo, Guanajuato and Tajitos as well as a number of other long term exploration prospects.

Fresnillo plc has mining concessions and exploration projects in Mexico, Peru and Chile.

Fresnillo plc's goal is to maintain the Group's position as the world's largest primary silver company and Mexico's largest gold producer.

 

1 Operations at Soledad-Dipolos are currently suspended.

 

FORWARD-LOOKING STATEMENTS

Information contained in this announcement may include 'forward-looking statements'. All statements other than statements of historical facts included herein, including, without limitation, those regarding the Fresnillo Group's intentions, beliefs or current expectations concerning, amongst other things, the Fresnillo Group's results of operations, financial position, liquidity, prospects, growth, strategies and the silver and gold industries are forward-looking statements. Such forward-looking statements involve risk and uncertainty because they relate to future events and circumstances. Forward-looking statements are not guarantees of future performance and the actual results of the Fresnillo Group's operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates, may differ materially from those described in, or suggested by, the forward-looking statements contained in this document. In addition, even if the results of operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates are consistent with the forward-looking statements contained in this document, those results or developments may not be indicative of results or developments in subsequent periods. A number of factors could cause results and developments to differ materially from those expressed or implied by the forward-looking statements including, without limitation, general economic and business conditions, industry trends, competition, commodity prices, changes in regulation, currency fluctuations (including the US dollar and Mexican Peso exchanges rates), the Fresnillo Group's ability to recover its reserves or develop new reserves, including its ability to convert its resources into reserves and its mineral potential into resources or reserves, changes in its business strategy and political and economic uncertainty.

 



[1] Au:Ag ratio of 80:1

 



This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 